Stage One July 2008 Images

Concrete barrier

Concrete barrier along the retaining wall constructed on the east side of the new Hasley Canyon northbound off-ramp.

Begin installation of geo-foam blocks

Begin installation of geo-foam blocks at the southwest corner of the Hasley Canyon and The Old Road.

Completion of installation of geo-foam blocks

Completion of installation of geo-foam blocks at the southwest corner of the Hasley canyon and The Old Road.

Installation of cabling for pre-stressing

Installation of cabling for pre-stressing of new Hasley Canyon Bridge.

Pre-stressing of cabling

Pre-stressing of cabling for the new Hasley Canyon Bridge.

Protective reinforcing concrete slab

Protective reinforcing concrete slab over geo-foam blocks.

Placing concrete over the geo-foam concrete block

Placing concrete over the geo-foam concrete block.

Begin installation of concrete block sound wall

Begin installation of concrete block sound wall along west side of The Old Road.

Continued installation of concrete block sound wall

Continued installation of concrete block sound wall.

New asphalt pavement

New asphalt pavement for new Hasley Canyon off-ramp west portion.

concrete block sound wall

Continued installation of concrete block sound wall.

Completed concrete block sound wall

Completed concrete block sound wall along west side of The Old Road.