Stage One March 2009 Images
Placement of reinforcing steel for Castaic Creek Bridge deck and barrier, I-5 southbound freeway bridge widening.
|
Finishing concrete pavement for Castaic Creek Bridge deck, I-5 southbound freeway bridge widening.
|
Place concrete curing and water tarps for Castaic Creek Bridge widening.
|
Cast-in-drilled-hole for Castaic Creek Bridge retrofit, I-5 freeway bridge widening.
|
Cast-in-drilled-hole for Castaic Creek Bridge retrofit, I-5 freeway bridge widening.
|
Construct shoring for Castaic Creek cast-in-drilled-hole concrete pile bridge retrofit.
|
Completed falsework installation for Castaic Creek Bridge deck for northbound I-5 freeway bridge widening.
|
Placement of reinforcing epoxy coated steel for new Hasley Canyon Bridge east approach slab
|
Placement of concrete for new Hasley Canyon Bridge east approach slab.
|
Placement of reinforcing steel cage for cast-in-drilled-hole concrete pile for Castaic Creek Bridge retrofit.
|
Placement of reinforcing steel cage for cast-in-drilled-hole concrete pile for Castaic Creek Bridge retrofit.
|
Lift assembled reinforcing steel cage for placing into the cast-in-drilled-hole for Castaic Creek Bridge retrofit.
|
Placement of reinforcing steel cage for cast-in-drilled-hole concrete pile for Castaic Creek Bridge retrofit.
|
Placement of reinforcing steel rebar and forms for new Hasley Canyon Bridge sidewalk and wall, north portion.
|
Construction of curb new curb for Sedona Way street median new alignment.
|
Place concrete for construction of the cast-in-drilled-hole concrete pile on southwest corner Castaic Creek I-5 bridge.
|
Install final roadway sign for the roundabout at Hasley Canyon Road and The Old Road.
|
|
|
|