Bid Price History

San Gabriel Reservoir Post-Fire Emergency Restoration Project
$92,225,000.00
04/13/2021
(-)
3
* Non-standard items are shaded yellow

Item CodeDescription% of Total ProjectQuantityUnitEngineer's EstimateLow Bidder Item BidAmountAverage Item BidMedian Item Bid
001.06.001CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $5,000) 0.01 1LS$5,000.00$5,000.00 $5,000.00 $5,000.00$5,000.00
001.06.003CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) 0.02 30MTH$500.00$500.00 $15,000.00 $500.00$500.00
001.06.009CONSTRUCTION SCHEDULE (AS-BUILT) (STIPULATED UNIT PRICE OF $2,000) 0 1LS$2,000.00$2,000.00 $2,000.00 $2,000.00$2,000.00
001.06.013PARTNERING (ALLOWANCE OF $25,000) 0.03 25000AL$1.00$1.00 $25,000.00 $1.00$1.00
001.07.001IMPLEMENTATION OF BMPS 0.16 30MTH$3,500.00$5,000.00 $150,000.00 $4,833.33$5,000.00
001.07.008IMPLEMENTATION OF THE SWPPP 0.33 30MTH$5,000.00$10,000.00 $300,000.00 $28,666.67$33,000.00
001.08.005OFFICE FACILITIES 0.39 60MTH$2,500.00$6,000.00 $360,000.00 $6,500.00$6,000.00
300.01.067CONCRETE REMOVAL (REINFORCED) 0.23 1607CY$250.00$130.00 $208,910.00 $126.67$130.00
301.02.005CRUSHED MISCELLANEOUS BASE 0.14 1254CY$135.00$100.00 $125,400.00 $95.67$100.00
302.05.013AC PAVEMENT 0.21 1270TON$130.00$150.00 $190,500.00 $125.67$130.00
 MOBILIZATION (2025) 0.54 1LS$1,000,000.00$500,000.00 $500,000.00 $1,083,333.33$1,250,000.00
 OUTLET TOWER A 0.10 41CY$2,000.00$2,200.00 $90,200.00 $3,076.67$3,300.00
 OUTLET TOWER B 0.09 37CY$2,000.00$2,200.00 $81,400.00 $3,490.00$4,000.00
 OUTLET TOWER C 0.10 40CY$2,000.00$2,200.00 $88,000.00 $3,335.00$3,700.00
 PREPARATION OF THE RESERVOIR DEWATERING PLAN (STIPULATED UNIT PRICE OF $10,000) 0.01 1LS$10,000.00$10,000.00 $10,000.00 $10,000.00$10,000.00
 PREPARATION OF THE FUGITIVE DUST CONTROL PLAN (STIPULATED UNIT PRICE OF $1,500/YEAR) 0.01 5YEAR$1,500.00$1,500.00 $7,500.00 $1,500.00$1,500.00
 PREPARATION OF SITE-SPECIFIC LEAD COMPLIANCE PLAN (STIPULATED UNIT PRICE OF $10,000) 0.01 1LS$10,000.00$10,000.00 $10,000.00 $10,000.00$10,000.00
 PREPARATION OF SITE-SPECIFIC HEALTH AND SAFETY PLAN (STIPULATED UNIT PRICE OF $10,000) 0.01 1LS$10,000.00$10,000.00 $10,000.00 $10,000.00$10,000.00
 PREPARATION OF THE SWPPP (STIPULATED UNIT PRICE OF $2,500) 0 1LS$2,500.00$2,500.00 $2,500.00 $2,500.00$2,500.00
 PREPARATION OF THE SURFACE WATER DIVERSION PLAN (STIPULATED UNIT PRICE OF $10,000) 0.01 1LS$10,000.00$10,000.00 $10,000.00 $10,000.00$10,000.00
 REMOVE HIGH VISIBILITY FENCING (2024) 0.01 2700LF$20.00$2.00 $5,400.00 $2.33$2.00
 REMOVE HIGH VISIBILITY FENCING (2025) 0.01 2700LF$20.00$2.00 $5,400.00 $2.42$2.00
 REMOVE HIGH VISIBILITY FENCING (2021) 0.01 2700LF$20.00$2.00 $5,400.00 $2.10$2.00
 REMOVE HIGH VISIBILITY FENCING (2022) 0.01 2700LF$20.00$2.00 $5,400.00 $2.18$2.00
 REMOVE HIGH VISIBILITY FENCING (2023) 0.01 2700LF$20.00$2.00 $5,400.00 $2.25$2.00
 SEPARATION AND DISPOSAL OF ORGANIC MATERIAL AND TRASH (2023) 0.05 23600TON$65.00$2.00 $47,200.00 $12.67$5.00
 SEPARATION AND DISPOSAL OF ORGANIC MATERIAL AND TRASH (2024) 0.05 23600TON$65.00$2.00 $47,200.00 $13.00$5.00
 SEPARATION AND DISPOSAL OF ORGANIC MATERIAL AND TRASH (2025) 0.05 23600TON$65.00$2.00 $47,200.00 $13.33$5.00
 SEPARATION AND DISPOSAL OF ORGANIC MATERIAL AND TRASH (2021) 0.03 16100TON$65.00$2.00 $32,200.00 $12.00$5.00
 SEPARATION AND DISPOSAL OF ORGANIC MATERIAL AND TRASH (2022) 0.05 23600TON$65.00$2.00 $47,200.00 $12.33$5.00
 SPILLWAY CHANNEL A 0.22 205CY$2,000.00$1,000.00 $205,000.00 $956.67$1,000.00
 SPILLWAY CHANNEL B 0.20 188CY$2,000.00$1,000.00 $188,000.00 $1,128.33$1,100.00
 SPILLWAY CHANNEL C 0.23 210CY$2,000.00$1,000.00 $210,000.00 $1,060.00$1,080.00
 SLUICEWAY TOWER REPAIR 0.98 1LS$769,179.00$900,000.00 $900,000.00 $736,666.67$900,000.00
 SLUICEWAY TUNNEL REPAIR 1.03 1LS$1,407,600.00$950,000.00 $950,000.00 $740,000.00$880,000.00
 STREET SWEEPER(S) 0.51 585DAYS$1,200.00$800.00 $468,000.00 $1,366.67$800.00
 STAINLESS STEEL PIPE AND PIPE TRENCH ENCASEMENT 0.41 1LS$823,400.00$375,000.00 $375,000.00 $1,875,000.00$800,000.00
 TRANSPORTATION AND DISPOSAL OF HAZARDOUS WASTE 0.08 1LS$1,000,000.00$75,000.00 $75,000.00 $35,666.67$25,000.00
 VEHICLE AND EQUIPMENT EMISSIONS REPORTING 0.07 30MTH$10,000.00$2,000.00 $60,000.00 $1,333.33$1,500.00
 WATER TRUCKS 1.27 585DAYS$2,400.00$2,000.00 $1,170,000.00 $3,766.67$2,300.00
 102" POLYMER COATED CSP, 12 GAGE 1.15 1773LF$385.00$600.00 $1,063,800.00 $624.33$600.00
 102" SEEP RING, 8 GA 12"X12" 0.09 9EA$2,000.00$9,000.00 $81,000.00 $9,310.00$9,000.00
 24" POLYMER COATED CSP, 12 GAGE 0.02 100LF$80.00$185.00 $18,500.00 $243.00$254.00
 24" CSP DROP INLET 0.02 7EA$1,000.00$2,000.00 $14,000.00 $3,613.33$2,500.00
 48" POLYMER COATED CSP, 12 GAGE 0.15 710LF$150.00$200.00 $142,000.00 $252.00$250.00
 36" POLYMER COATED CSP, 12 GAGE 0.79 3954LF$120.00$185.00 $731,490.00 $203.67$185.00
 36" CSP DROP INLET 0.02 8EA$1,500.00$2,200.00 $17,600.00 $3,811.67$2,700.00
 72" POLYMER COATED CSP, 12 GAGE 0.37 805LF$300.00$425.00 $342,125.00 $524.67$484.00
 72" SEEP RING, 8 GA 12"X12" 0.05 10EA$2,000.00$5,000.00 $50,000.00 $5,468.33$5,000.00
 4X4 MAIN OUTLET TOWER SLIDE GATE 0.20 1LS$89,700.00$185,000.00 $185,000.00 $256,666.67$250,000.00
 ABANDON EXISTING CSP 0.43 1LS$159,640.00$400,000.00 $400,000.00 $479,216.67$425,000.00
 66" POLYMER COATED CSP, 12 GAGE 0.46 1061LF$275.00$400.00 $424,400.00 $410.67$400.00
 66" SEEP RING, 8 GA 12"X12" 0.04 9EA$2,000.00$4,500.00 $40,500.00 $4,968.33$4,500.00
 6X6 SLUICE GATE AND HYDRAULIC ACTUATOR REHABILITATION 0.30 1LS$373,750.00$275,000.00 $275,000.00 $350,000.00$375,000.00
 ACCESS SHAFT 0.38 7EA$15,000.00$50,000.00 $350,000.00 $59,470.00$62,410.00
 CLEARING AND GRUBBING (RESERVOIR) 0.17 78AC$3,300.00$2,000.00 $156,000.00 $2,000.00$2,000.00
 CLEARING AND GRUBBING (SPS) 0.13 47AC$3,300.00$2,500.00 $117,500.00 $4,166.67$3,000.00
 CONCRETE GUTTER, TYPE A 0.18 151CY$1,000.00$1,100.00 $166,100.00 $1,041.67$1,100.00
 CONCRETE GUTTER, TYPE B 0.37 285CY$1,000.00$1,200.00 $342,000.00 $1,123.33$1,200.00
 CONCRETE GUTTER, TYPE C 0.05 31CY$1,000.00$1,400.00 $43,400.00 $1,228.33$1,285.00
 CSP RISER 0.08 6EA$10,000.00$12,500.00 $75,000.00 $14,113.33$12,500.00
 EXCAVATION, DISPOSAL, AND PLACEMENT OF SEDIMENT (2021) 8.28 714000CY$14.20$10.70 $7,639,800.00 $11.50$10.70
 EXCAVATION, DISPOSAL, AND PLACEMENT OF SEDIMENT (2022) 11.38 1047000CY$14.40$10.02 $10,490,940.00 $11.46$10.02
 EXCAVATION, DISPOSAL, AND PLACEMENT OF SEDIMENT (2023) 11.40 1047000CY$14.60$10.04 $10,511,880.00 $11.44$10.04
 EXCAVATION, DISPOSAL, AND PLACEMENT OF SEDIMENT (2024) 11.42 1047000CY$14.80$10.06 $10,532,820.00 $11.39$10.06
 EXCAVATION, DISPOSAL, AND PLACEMENT OF SEDIMENT (2025) 11.44 1047000CY$15.00$10.08 $10,553,760.00 $11.34$10.08
 EROSION PROTECTION BLANKET 0.03 63152SY$5.00$0.50 $31,576.00 $0.83$1.00
 FACING SLAB A 0.55 360CY$2,000.00$1,400.00 $504,000.00 $921.67$685.00
 FACING SLAB B 0.39 258CY$2,000.00$1,400.00 $361,200.00 $992.33$800.00
 FACING SLAB C 0.26 168CY$2,000.00$1,400.00 $235,200.00 $1,051.00$880.00
 HIGH VISIBILITY FENCING (2025) 0.01 2700LF$20.00$5.00 $13,500.00 $5.53$5.00
 HIGH VISIBILITY FENCING (2021) 0.03 2700LF$20.00$10.00 $27,000.00 $6.58$5.75
 HIGH VISIBILITY FENCING (2022) 0.01 2700LF$20.00$5.00 $13,500.00 $5.07$5.00
 HIGH VISIBILITY FENCING (2023) 0.01 2700LF$20.00$5.00 $13,500.00 $5.22$5.00
 HIGH VISIBILITY FENCING (2024) 0.01 2700LF$20.00$5.00 $13,500.00 $5.37$5.00
 HYDRAULIC POWER UNIT AND CONTROL PANEL 0.18 1LS$279,450.00$165,000.00 $165,000.00 $468,333.33$540,000.00
 IMPLEMENTATION OF THE FUGITIVE DUST CONTROL PLAN 0.03 30MTH$1,500.00$1,000.00 $30,000.00 $13,000.00$15,000.00
 IMPLEMENTATION OF SITE-SPECIFIC LEAD COMPLIANCE PLAN 0.03 1LS$2,500,000.00$30,000.00 $30,000.00 $29,333.33$30,000.00
 IMPLEMENTATION OF SITE SPECIFIC HEALTH AND SAFETY PLAN 0.02 1LS$150,000.00$20,000.00 $20,000.00 $154,666.67$44,000.00
 IMPLEMENTATION OF THE RESERVOIR DEWATERING PLAN (2021) 2.74 1LS$2,000,000.00$2,522,900.00 $2,522,900.00 $5,924,300.00$5,250,000.00
 IMPLEMENTATION OF THE RESERVOIR DEWATERING PLAN (2022) 1.08 1LS$1,500,000.00$1,000,000.00 $1,000,000.00 $4,200,000.00$3,600,000.00
 IMPLEMENTATION OF THE RESERVOIR DEWATERING PLAN (2023) 1.08 1LS$1,500,000.00$1,000,000.00 $1,000,000.00 $1,816,666.67$2,200,000.00
 IMPLEMENTATION OF THE RESERVOIR DEWATERING PLAN (2024) 0.87 1LS$1,500,000.00$800,000.00 $800,000.00 $1,483,333.33$1,800,000.00
 IMPLEMENTATION OF THE RESERVOIR DEWATERING PLAN (2025) 0.22 1LS$1,500,000.00$200,000.00 $200,000.00 $1,186,666.67$1,560,000.00
 IMPLEMENTATION OF THE SURFACE WATER DIVERSION PLAN (2023) 1.63 1LS$1,500,000.00$1,500,000.00 $1,500,000.00 $3,083,333.33$2,200,000.00
 IMPLEMENTATION OF THE SURFACE WATER DIVERSION PLAN (2024) 1.36 1LS$1,500,000.00$1,250,000.00 $1,250,000.00 $2,816,666.67$1,800,000.00
 IMPLEMENTATION OF THE SURFACE WATER DIVERSION PLAN (2025) 0.54 1LS$1,500,000.00$500,000.00 $500,000.00 $2,580,000.00$1,800,000.00
 IMPLEMENTATION OF THE SURFACE WATER DIVERSION PLAN (2021) 3.84 1LS$2,000,000.00$3,539,099.00 $3,539,099.00 $9,746,366.33$9,200,000.00
 IMPLEMENTATION OF THE SURFACE WATER DIVERSION PLAN (2022) 1.90 1LS$1,500,000.00$1,750,000.00 $1,750,000.00 $4,483,333.33$5,000,000.00
 MAIN OUTLET TOWER REHABILITATION 2.60 1LS$3,249,900.00$2,400,000.00 $2,400,000.00 $1,383,333.33$1,500,000.00
 MAIN OUTLET TUNNEL REPAIR 1.25 1LS$940,700.00$1,150,000.00 $1,150,000.00 $670,000.00$600,000.00
 NEW STEEL WALKWAY, LADDERS, AND MISC. METAL 1.36 1LS$1,261,550.00$1,250,000.00 $1,250,000.00 $3,250,000.00$3,150,000.00
 MOBILIZATION (2021) 4.12 1LS$1,000,000.00$3,800,000.00 $3,800,000.00 $6,100,000.00$3,800,000.00
 MOBILIZATION (2022) 2.71 1LS$1,000,000.00$2,500,000.00 $2,500,000.00 $3,401,401.00$3,500,000.00
 MOBILIZATION (2023) 2.71 1LS$1,000,000.00$2,500,000.00 $2,500,000.00 $1,750,000.00$1,500,000.00
 MOBILIZATION (2024) 1.41 1LS$1,000,000.00$1,300,000.00 $1,300,000.00 $1,350,000.00$1,300,000.00
 Total Percent100   Total Amount$92,225,000.00