Stormwater Engineering Projects

Picture of Santa Anita Dam

ANNOUNCEMENTS

Anticipated Start of Construction

  1. Santa Anita Debris Dam Seismic Strengthening and Enlargement Project - Spring 2023
  2. Santa Anita Headworks Improvements Project - Summer 2023

Construction Status

  1. Santa Anita Spreading Grounds Enlargement and Enhancement Project (Phase 2) - The construction has been completed
  2. Santa Anita Dam Spillway Modification Project - The construction has been completed

April 2020 - A change in the scope of work was made to the Santa Anita Debris Dam Seismic Strengthening and Enlargement Project and the Santa Anita Headworks Improvements Project resulting in preparation of an Addendum to the previously approved CEQA.

July 2015 - The Final Initial Study/Mitigated Negative Declaration was adopted by the County of Los Angeles Board of Supervisors on July 14, 2015. The Notice of Determination was posted at the County of Los Angeles Registrar-Recorder/County Clerk from July 20, 2015 through August 19, 2015. No legal challenges were received. Regulatory permits are being obtained during the design phase for each project component.

April 2015 - The Final Initial Study/Mitigated Negative Declaration (IS/MND) has been released and includes a complete Response To Comments, the Mitigation Monitoring & Reporting Program, and Errata. Click here to view the document or see the "CEQA Documents" subsection under RESOURCES.

December 2014 - The IS/MND comment period has closed. The IS/MND was released for Public Review on Monday, October 20, 2014. The comment period was 45 days and ended December 4, 2014. Thank you to all who submitted comments. The documents are still available to view in the RESOURCES Section below and a Response to Comments will also be prepared and posted once available.

November 2014 - A Public Information Meeting was held on Wednesday, November 5, 2014 from 6-8pm at the Arcadia City Council Chambers. Staff from the Los Angeles County Flood Control District (LACFCD), BonTerra Psomas (environmental consultant), and Arellano & Associates (public relations sub consultant) presented the project and the IS/MND. Following the presentation, there was a group Question and Answer session and then a time for guests to visit topical breakout stations for further discussion. Materials from the Public Information Meeting are available in the RESOURCES Section below.

PROJECT SUMMARY

The proposed Project would modify three existing flood management and water conservation facilities along the Santa Anita Canyon Watershed, including the Santa Anita Dam (Dam), the Santa Anita Headworks (Headworks), and the Santa Anita Debris Dam (Debris Dam). The Project would improve the LACFCD facilities to better manage stormwater runoff and improve public safety by addressing seismic safety and other structural issues, as well as by preventing flood damage to downstream communities.

This project is partially funded by a State Proposition 1E grant as well as funds from the City of Arcadia, City of Sierra Madre, and the Raymond Basin Management Board.

RESOURCES

General Information

Public Information Meeting Materials

CEQA Documents

CONTACTS

For more information on the project or to be added to the project mailing list, please contact DAMPROJECTS@dpw.lacounty.gov

Updated on: 09/21/2023